27th Street Bridge

Night closures of 27th Street and S. Grand Avenue Intersection on June 25 & 26

27th Street Bridge construction crews are scheduled to lower a new water line into the S. Grand Ave. intersection on Tuesday, June 25 and Wednesday, June 26. To compete this work, night closures in the area will be required. At approximately 8 p.m. each evening, the 27th Street Bridge and the intersection of S. Grand Ave. and 27th Street will close until the early hours of the morning. Water service interruptions are not anticipated.

During closures, 27th Street Bridge traffic will be detoured via 8th Street. S. Grand Avenue motorists will be redirected via Colorado Highway 82. Local business and residential access will remain open.

PROJECT BULLETIN

Whenever possible, crews are limiting work with traffic impacts to off peak hours. However, due to the dynamic nature of the construction activities and site constraints, intermittent lane closures on the bridge may be required during peak times.

Motorists should expect ongoing holds and bridge lane closures during off peak hours off-peak hours (before 7AM, between 8:30 AM-4:30 PM, and after 6 PM).

To maximize the progress on the bridge abutments, crews will access the site as early as sunup to begin daily preparations for drilling work to begin at 7 AM As needed, crews will continue work as late as 9 PM.

Construction on Saturdays, 8 AM to 6 PM, is expected to be more frequent and, if necessary, some construction activities may occur on Sundays.

Do not block intersections or the roundabout and follow flagger instructions.

Call the hotline to hear the latest traffic impact information: 970-618-5379.

Sign up here for News and Updates


  1. Construction info.
  2. Schedule
  3. About

Construction on the 27th Street Bridge (also known as Sunlight Bridge) project began on January 2, 2019. As soil nail walls near completion (targeted to be complete beginning of April), crews are shifting focus to micropile construction. With this new work activity, expect to see some changes to project impacts.

The construction team will make every attempt to avoid lane closures during the peak times, especially the morning rush, but this is a very dynamic site. At any given time, materials and crews are moving in and out of the very limited site areas, working on complex construction activities. It is like replacing the floor of a gymnasium while keeping a basketball game going.

Thank you in advance for your patience.

Bus Stop Service Notice

The 27th Street/S. Grand Ave. Ride Glenwood bus stop will close until further notice on Monday, April 22 with the spring schedule change. Service will be relocated to the 27th BRT station on CO-82. This stop will be closed for the duration of project construction. The last day of service at this location will be Sunday, April 21.

Micropile Construction

Construction crews began construction on the micropiles for the new pedestrian and traffic bridges on March 18. Expect heavy machinery and louder construction noise associated with these operations which will be ongoing for approximately the next two months. Construction on Saturdays and Sundays is expected to be more frequent.

Micropiles are deep foundation elements constructed using a high-strength steel rod surrounded by grout in a small, 10” diameter steel pipe. The project is using micropiles to enable accelerated bridge construction (ABC construction) to construct the foundation of the new bridges on location while keeping the existing bridge open and minimizing the overall duration of the project.

Additional Construction Information

Work is expected to take place throughout 2019 for this project, which includes the traffic bridge, pedestrian bridge, and the roundabout. The current 27th Street Bridge and pedestrian bridge will remain open until the replacement of the bridges occurs in summer 2019. Pedestrian and river access will largely remain open; however, there will be periodic holds and some full closures for critical overhead work later in 2019.

Business access will remain open. Follow flagger instructions and construction signage. There will be daily lane closures on both sides of the bridge. Motorists should also expect delays for travel along South Grand Ave. between 23rd Street and 29th Street. (Please note that CO-82 switches from Grand Ave. to Glen Ave. south of 23rd Street).

In the summer of 2019, construction crews will build the new replacement bridge just south of the existing bridge. The old bridge will be deconstructed, and the new bridge will be slid into place. This technique, called a bridge slide, will minimize impacts to traffic, pedestrians, utilities, and river users while replacing the existing vehicle bridge. A new and separate pedestrian bridge also will be built to the north and all bridge piers will be removed from the Roaring Fork River.

27th Street Bridge Project Information
27thStreetBridge@gmail.com
Phone: 970-618-5379 (call or text)

Tips for Motorists:

  • Plan extra travel time through the area especially during peak times. Delays have ranged between approximately 5 and 25 minutes and are intermittent in nature.
  • Do not block the roundabout and follow flagger instructions. This helps to keep traffic flowing.
  • Use alternate routes (CO-82). Midland Avenue should be used for local traffic only.
    • Walk, bike and carpool whenever possible. The fewer cars trying to get through the area will mean shorter delays.
    • Scheduled impacts are communicated via the ConeZone email update, city Facebook, city Twitter and the project phone. Tune in to your platform of choice to see the latest information.
    • All work is weather dependent and subject to change based on conditions encountered.