Dates, times and construction activities are subject to change. Please plan extra travel time and follow postage signage when driving through construction areas.
Highway 6 and Storm King Rd. (by West Glenwood Mall)
- June 7-18, 9 a.m.-4 p.m.
- One lane road with shoulder work and sidewalk closures for utility work
- View map >>
Midland Ave. between 8th St. and 13th St.
- June 8-9, 9 a.m.-4 p.m.
- One lane road with shoulder work for fiber installation
CDOT CO 82 and CO 133 Signal Replacement Project
- The CDOT signal replacement project on CO 82/Grand Avenue will occur at 11th Street and 14th Street and on CO 133 at Village Road and Meadowood Drive. Motorists should plan for street closures, turn lane closures and lane closures on CO 82.
- Delays anticipated.
- View anticipated schedule for the week of June 7 >>
- Read more >>
Roaring Fork Marketplace/Blake Ave.
- June 1-30
- Entrance closure at CO 82 and Blake Ave. (by McDonalds) for removals and paving
- Use 29th Street for business access.
- Bus stop closed until August. Use 27th Street station.
- View map >>
South Midland Ave. (Keep South Midland Moving Project)
- Motorists should anticipate a lane shift through the work area on South Midland. The traffic lane shift is necessary for access to the roadway for utility work and downhill wall construction.
- Regular lane closure hours are 9 a.m.-4 p.m. on weekdays and 7 a.m.-6 p.m. on Saturdays.
- Read more >>
Xcel Glenwood Springs – Mitchell Creek Electric Transmission Line Rebuild Project