Happy Labor Day
Following the successful completion of the phase of roundabout pavement core filling, all construction work on South Midland will be paused from 12:00 p.m. on Friday, September 3, until Tuesday, September 7.
North Closure in Park West Begins September 7
Beginning Tuesday, September 7, the north neighborhood entrance to Park West will be closed for construction crews working to improve the line of sight. All motorists and pedestrians will enter and exit via the south entrance.
See the map >>
CCC Meeting Rescheduled to September 15
The next meeting of the South Midland Community Communications Coalition (CCC) has been rescheduled to Wednesday, Sept. 15, 2021, from 4:30 p.m. – 6:00 p.m. at Sullivan Park in Glenwood Springs. The project construction team will be on hand to give tours, answer questions, provide updates. Everyone is welcome. Please RSVP to southmidlandproject@gmail.com or 970-618-5379.
About the South Midland Reconstruction Project
The 18-month-long reconstruction project will better serve the South Glenwood Springs Community for years to come. The South Midland corridor had been prone to potholes, poor site lines, regular rockfall events, and there were gaps in pedestrian infrastructure amidst the backdrop of rising traffic volumes. Approximately one-third of Glenwood Springs residents use this corridor, so that is why it is critical to Keep South Midland Moving. Construction activities began in December 2020 and will continue through Summer 2022.
PROJECT INFORMATION | INFORMACIÓN SOBRE EL PROYECTO
Phone (call or text) | Teléfono (llamar o por texto): 970-618-5379
Email: southmidlandproject@gmail.com
Webpage | Sitio web: cogs.us/SouthMidland
#KeepSouthMidlandMoving
###