Crews on South Midland will be working extended hours this week from Monday through Wednesday. All construction will pause beginning 4 p.m. on Wednesday, November 24 and resume on Monday, November 29. Happy Thanksgiving!
Español: https://cogs.us/CivicAlerts.aspx?AID=659
Happy Thanksgiving from the South Midland Project Team
Crews in the South Midland corridor will be working until 4 p.m. on Monday, November 22 through Wednesday, November 24. Construction activities along the South Midland corridor will then pause over the Thanksgiving holiday weekend. No lane closures will be in place beginning 4 p.m. on Wednesday, November 24 through Sunday, November 28. Regularly scheduled construction project work will resume on Monday, November 29.
Have a happy and safe Thanksgiving weekend on behalf of everyone on the Keep South Midland Moving team.
Project Look Ahead
- Storm sewer work on Sopris Drive
- Sidewalk concrete for Downhill Wall 2
- Wall 2 pedestrian railing
- Miscellaneous concrete aprons and drives
Take a look! Check out just a few of the improvements that have been made along the South Midland corridor. Stay tuned for a 2021 project wrap up.

PROJECT INFORMATION | INFORMACIÓN SOBRE EL PROYECTO
Phone (call or text) | Teléfono (llamar o por texto): 970-618-5379
Email: southmidlandproject@gmail.com
Webpage | Sitio web: cogs.us/SouthMidland
#KeepSouthMidlandMoving
###