Crews on South Midland will operate until 4 p.m. today, Thursday, March 17, to continue fire hydrant installation and road subgrade work.
Tomorrow, Friday, March 18, South Midland construction crews will work from 7 a.m. – 5 p.m. to complete a critical water main tie-in. Water will also be shut off at the Thunder River condos tomorrow during the water tie-in work. Crews will work on Saturday from 8 a.m. – 5 p.m.
For the week of March 21, crews will be working until 4 p.m. each day while Sopris Elementary is not in session for spring break.